14,000 S.F. super smooth concrete slab with equipment purchased from Skatewave and Spohn Ranch created one of the finest skateboard parks in the area. Challenges presented on this project included quality control of the concrete pour as well as detailed grading to accommodate the flat portions of the park, transition area to the bowl and grading for the bowl and deck.

Other considerations included planning for equipment spacing, coordinating with the equipment designers, coordinating deliveries, ambient temperatures, construction phase, concrete curing and finishing. We are pleased to acknowledge use and compliments by many professional skateboarders.

Client:
Township of Falls
Completion:
2009
Project Type:
Capital Improvement
Project Engineer:
Joseph G. Jones, PE, CFM